QUESTION IMAGE
Question
question 77 of 100 - multiple choice
pipe strain must be corrected?
a after alignment is complete
b pipe strain does not have to be corrected
c while performing alignment
d before starting alignment
Identify the core requirement of shaft alignment
Shaft alignment cannot be performed accurately if external forces, such as pipe strain, are acting on the machinery casings.
Determine the correct sequence of operations
Pipe strain must be measured and corrected before starting the actual shaft alignment process to prevent the piping from pulling or pushing the machinery out of its aligned position.
Snap & solve any problem in the app
Get step-by-step solutions on Sovi AI
Photo-based solutions with guided steps
Explore more problems and detailed explanations
- (A) after alignment is complete
- (B) pipe strain does not have to be corrected
- (C) while performing alignment
- (D) before starting alignment (Correct answer)