as a project plan for a new apartment building is being built, a constr…

Question

as a project plan for a new apartment building is being built, a construction consultant reminds a project manager that weather delays could impact the opening of the complex. which project plan document should be updated to include this possibility?

schedule
risk register
scope
budget

Explanation:

Brief Explanations

The question is about project management in construction, and the risk of weather delays is a project risk. The Risk register is the document that tracks and manages project risks, so it should be updated to include this possibility. The other options (Schedule, Scope, Budget) are not primarily for recording risks.

Answer:

B. Risk register