the maxit corporation has a standard costing system in which variable manufacturing overhead is assigned to production on the basis of standard machine - hours. the following data are available for july:
- actual variable manufacturing overhead cost incurred: $26,140
- actual machine - hours worked: 3,200 hours
- variable overhead rate variance: $5,820 u
- total variable overhead spending variance: $8,140 u
the variable overhead efficiency variance for july is:
multiple choice
$13,960 f
$2,320 f
$2,320 u
$13,960 u
Step1: Recall the formula for total variable overhead spending variance
The formula for total variable overhead spending variance is \( \text{Total variable overhead spending variance}=\text{Variable overhead rate variance}+\text{Variable overhead efficiency variance} \).
Step2: Rearrange the formula to solve for variable overhead efficiency variance
We can rewrite the formula as \( \text{Variable overhead efficiency variance}=\text{Total variable overhead spending variance}-\text{Variable overhead rate variance} \).
Step3: Substitute the given values into the formula
We are given that the total variable overhead spending variance is \( \$8,140\ U \) (unfavorable, so \(+ 8140\)) and the variable overhead rate variance is \( \$5,820\ U \) (unfavorable, so \(+5820\)).
Since the total spending variance (\(8140\ U\)) and rate variance (\(5820\ U\)) are both unfavorable, and \(8140>5820\), the efficiency variance is also unfavorable.
Snap & solve any problem in the app
Get step-by-step solutions on Sovi AI
Photo-based solutions with guided steps
Explore more problems and detailed explanations
\(\$2,320\ U\)