question 89 of 93 you are filling out a change - order form. toward its…

Question

question 89 of 93
you are filling out a change - order form. toward its end, you explain how you will return affected hardware and software to its original state if the change fails. what is this plan called?

  • backout plan
  • risk analysis
  • rollback plan
  • system image plan

Explanation:

Brief Explanations

A backout plan details how to return affected hardware and software to their original state if a change fails. Risk analysis assesses potential risks, a rollback plan is similar but may not be as comprehensive in reverting to the exact original state, and a system - image plan is related to creating and using system images.

Answer:

Backout plan