india is a project manager at an advertising firm, in charge of develop…

Question

india is a project manager at an advertising firm, in charge of developing a new ad campaign for a client. today, she learned from her boss that the client wants the campaign completed next week instead of next month. which of these would be an agile way for india to adapt to this unexpected event? inform her boss that the clients request is simply not possible. create a project plan around the new deadline and ask for help as needed. hand management of this particular project over to someone else. cut down on sleep and exercise to squeeze in more working hours.

Explanation:

Brief Explanations

Agile methodology emphasizes adaptability, collaboration, and responding to change. In this situation, creating a new project plan around the shortened deadline and seeking help when needed aligns with agile principles (adapting to change, working collaboratively). The other options: refusing the request (not agile), handing over the project (not taking ownership), and overworking (unsustainable, not agile) are not appropriate.

Answer:

B. Create a project plan around the new deadline and ask for help as needed.