all members of a construction crew work at the same pace. four of them working together can pour a foundation in 32 hours. how many hours would the job take if the number of workers:
increased 2 times
Identify the relationship
$$
\text{Workers} \times \text{Hours} = \text{Total Work (constant)}
$$
Calculate the constant total work
$$
4 \times 32 = 128 \text{ worker-hours}
$$
Determine the new time
$$
LATEXBLOCK0
$$
Snap & solve any problem in the app
Get step-by-step solutions on Sovi AI
Photo-based solutions with guided steps
Explore more problems and detailed explanations
16 hours