Question
standard costs are used in the calculation of:
multiple choice
price and quantity variances.
price variances only.
quantity variances only.
price, quantity, and sales variances.
quantity and sales variances.
Standard costs are integral in variance analysis. Price variance is calculated as (Actual Price - Standard Price) × Actual Quantity. Quantity variance is (Actual Quantity - Standard Quantity) × Standard Price. Both use standard costs. Sales variance is more about revenue (not directly cost - based standard in the same sense as price and quantity variances for costs).