select all that apply、a manufacturing cycle efficiency of 40% means that ________.the typical order is being worked on 40% of the timevalue - added activities are being performed 40% of the timevalue - added activities are being performed 60% of the time40% of the companys time is spent on non - value - added activitiesneed help? review these concept resources.read about the concept

Explanation:

Brief Explanations

Manufacturing cycle efficiency (MCE) is calculated as \(MCE=\frac{\text{Value - added time}}{\text{Total manufacturing time}}\). A 40% MCE means that value - added activities consume 40% of the total manufacturing time. Non - value - added time would then be \(1 - 0.4=0.6\) or 60% of the total time. The first option about the typical order being worked on 40% of the time is not the correct interpretation of MCE. The fourth option is wrong as 60% (not 40%) of the time is spent on non - value - added activities.

Answer:

value - added activities are being performed 40% of the time