QUESTION IMAGE
Question
ross hopkins, president of hopkins hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels
a) the expected (estimated) time for activity c is 13.67 weeks (round your response to two decimal places.)
b) the variance for activity c is 2.78 weeks (round your response to two decimal places )
c) based on the calculation of the estimated times, the critical path is a - c - f - h - j - k
d) the estimated time for the critical path is □ weeks (round your response to two decimal places )
Step1: Calculate expected time for each activity on critical path
The formula for expected time \(t_{e}=\frac{a + 4m + b}{6}\).
For \(A\): \(t_{eA}=\frac{6+4\times9 + 12}{6}=\frac{6+36+12}{6}=\frac{54}{6}=9\)
For \(C\): \(t_{eC} = 13.67\) (given)
For \(F\): \(t_{eF}=\frac{6+4\times9+21}{6}=\frac{6 + 36+21}{6}=\frac{63}{6}=10.5\)
For \(H\): \(t_{eH}=\frac{2+4\times2+2}{6}=\frac{2+8 + 2}{6}=\frac{12}{6}=2\)
For \(J\): \(t_{eJ}=\frac{6+4\times8+14}{6}=\frac{6+32+14}{6}=\frac{52}{6}\approx8.67\)
For \(K\): \(t_{eK}=\frac{1+4\times1+4}{6}=\frac{1+4+4}{6}=\frac{9}{6}=1.5\)
Step2: Sum up expected times of activities on critical path
\(T=t_{eA}+t_{eC}+t_{eF}+t_{eH}+t_{eJ}+t_{eK}\)
\(T = 9+13.67+10.5+2+8.67+1.5\)
\(T=45.34\)