QUESTION IMAGE
Question
identify where to place the fifth pass for this 2g weld.
bead b
bead e
bead a
bead f
bead d
bead c
Analyze the 2G weld pass sequence
Using the 2G Weld Sequence and Horizontal Groove Welding knowledge points
In horizontal groove welding (2G position), multi-pass welds are deposited in a specific sequence to prevent sagging and ensure proper fusion:
- First Pass (Root Pass): Bead A is placed at the root of the joint.
- Second Pass: Bead B is placed along the upper bevel of the joint.
- Third Pass: Bead E is placed below Bead B to support it and fill the lower portion.
- Fourth Pass: Bead C is placed at the top of the next layer along the upper plate.
- Fifth Pass: Bead F is placed directly below Bead C to continue filling the joint.
- Sixth Pass: Bead D is the final cover pass at the bottom.
Therefore, the fifth pass corresponds to Bead F.
Snap & solve any problem in the app
Get step-by-step solutions on Sovi AI
Photo-based solutions with guided steps
Explore more problems and detailed explanations
- Bead B
- Bead E
- Bead A
- Bead F (Correct answer)
- Bead D
- Bead C