an external vendor is attempting to sell a team member a lower - quality grade of wood to build stands inside a gymnasium. what should the team member do?
options:
accept the discounted materials from the vendor.
report the situation to the project manager.
report the vendor to the appropriate regulation authorities.
report the situation to the project sponsor.
Lower-quality wood for gymnasium stands poses safety risks. The team member’s immediate line of reporting in project contexts is the project manager, who oversees material standards and risk mitigation. Reporting to the project manager ensures prompt, appropriate action aligned with project protocols.
Snap & solve any problem in the app
Get step-by-step solutions on Sovi AI
Photo-based solutions with guided steps
Explore more problems and detailed explanations
Report the situation to the project manager.