Question
for the construction of new stands inside a gymnasium, which project task is considered to be a procurement?
finalizing a contract to build the stands.
starting the bid process for a vendor to build the stands.
obtaining the wood to build the stands.
securing the internal designers availability to design the stands.
En gestión de proyectos, el abastecimiento (procurement) implica obtener bienes o servicios. "Obtaining the wood to build the stands" es adquirir un recurso (madera) necesario para la construcción, lo que se ajusta a la definición de abastecimiento. Las otras opciones: finalizar contrato es parte posterior, iniciar licitación es el proceso previo, y asegurar disponibilidad de diseñador es gestión de recursos humanos, no abastecimiento.
Snap & solve any problem in the app
Get step-by-step solutions on Sovi AI
Photo-based solutions with guided steps
Explore more problems and detailed explanations
Obtaining the wood to build the stands.