qs 21-2 (algo) flexible budget cost calculations lo p1
based on predicted production of 24,800 units, a company budgets $340,000 of fixed costs and $446,400 of variable costs. if the company actually produces 19,600 units, what are the flexible budget amounts of fixed and variable costs?
flexible budget
item | variable amount per unit | total fixed cost | 19,600 units
Calculate variable cost per unit
$$
\text{Variable Cost per Unit} = \frac{\$446,400}{24,800\text{ units}} = \$18.00\text{ per unit}
$$
Determine flexible budget costs at actual production level
$$
LATEXBLOCK0
$$
Summarize flexible budget table values
$$
LATEXBLOCK1
$$
Snap & solve any problem in the app
Get step-by-step solutions on Sovi AI
Photo-based solutions with guided steps
Explore more problems and detailed explanations
| Item | Variable Amount per Unit | Total Fixed Cost | 19,600 units |
|---|---|---|---|
| Fixed costs | \$340,000 | \$340,000 |