if dominik completes a project by himself, it will take him 8 hours. working with katarina, it will take them 5 hours.
| rate (part/hour) | time (hours) | part of project completed | |
|---|---|---|---|
| katarina | \\(r\\) | 5 | \\(5r\\) |
if they work together, what is the missing value from the table that represents the part of the project dominik will complete?
\\(\bigcirc\\) \\(8r\\)
\\(\bigcirc\\) \\(8(5)\\)
\\(\bigcirc\\) \\(\frac{1}{8}r\\)
\\(\bigcirc\\) \\(\frac{1}{8}(5)\\)
Step1: Recall Work Rate Formula
The formula for work done is \( \text{Work} = \text{Rate} \times \text{Time} \).
Step2: Apply Formula to Dominik's Work
Dominik's rate is \( \frac{1}{8} \) part/hour and time is 5 hours. So, work done by Dominik is \( \frac{1}{8} \times 5 \), which is \( \frac{1}{8}(5) \).
Snap & solve any problem in the app
Get step-by-step solutions on Sovi AI
Photo-based solutions with guided steps
Explore more problems and detailed explanations
\(\frac{1}{8}(5)\) (the last option)