for staff producing drain caps, a shift is eight hours, including one hour for breaks and lunch. demand can be met by completing 70 units per shift.
how many minutes is the takt time for the process?
6.85
6
6.9
7
Calculate available production time
To find the available production time, we subtract the non-productive time (breaks and lunch) from the total shift duration.
Total shift time is \(8\text{ hours}\).
Breaks and lunch take \(1\text{ hour}\).
Available production time in hours:
Convert available time to minutes
Since the question asks for the takt time in minutes, we convert the available production time from hours to minutes.
Using the Six Sigma Metrics concept, we convert the time:
Calculate the takt time
Takt time is defined as the available production time divided by the customer demand.
The required demand is \(70\text{ units}\).
Snap & solve any problem in the app
Get step-by-step solutions on Sovi AI
Photo-based solutions with guided steps
Explore more problems and detailed explanations
- (A) 5.85
- (B) 6 (Correct answer)
- (C) 6.9
- (D) 7