question 4 (3.333 points)
for an electrical contractor who specializes in health care construction containing many varied work activities, which method should be used to determine percent complete?
a) cost to cost method
b) labor hours method
c) work quantity method
d) all impact the contractor in the same way

Explanation:

Brief Explanations

The work quantity method is suitable for projects with varied work activities. It directly measures the physical progress of work completed. The cost - to - cost method focuses on costs, which may not accurately reflect progress in a project with diverse tasks. The labor - hours method emphasizes labor input, but different tasks may have different labor efficiencies. Since the electrical contractor has many varied work activities, the work quantity method is the most appropriate.

Answer:

C. Work quantity method