which of the following must be done before operating a crane? select all that apply.
- barricading areas within the swing radius
- contacting power line owners
- leveling the crane
- making other personnel aware of hoisting activities
if you need to review this content, it can be found in the using cranes module of the cranes topic
To determine the correct options for what must be done before operating a crane, we analyze each option:
- Barricading areas within the swing radius: This is crucial for safety to prevent people/objects from entering the dangerous swing area of the crane.
- Contacting power line owners: Power lines are a major hazard, so notifying owners helps in planning to avoid contact.
- Leveling the crane: A level crane is necessary for stability during operation to prevent tipping.
- Making other personnel aware of hoisting activities: Communicating with others on-site ensures they stay safe and know the crane's operations.
All these actions are standard safety and preparatory steps before crane operation.
Snap & solve any problem in the app
Get step-by-step solutions on Sovi AI
Photo-based solutions with guided steps
Explore more problems and detailed explanations
A. Barricading areas within the swing radius
B. Contacting power line owners
C. Leveling the crane
D. Making other personnel aware of hoisting activities