Question
which of the following must be done before operating a crane?
select all that apply.
- barricading areas within the swing radius
- contacting power line owners
- leveling the crane
- making other personnel aware of hoisting activities
Brief Explanations
- Barricading areas within the swing radius: This is necessary to prevent unauthorized personnel from entering the dangerous zone where the crane's boom swings, reducing accident risks.
- Contacting power line owners: If there are power lines near the crane operation area, contacting their owners helps in planning safe operations, like getting clearance or knowing about power line movements.
- Leveling the crane: A leveled crane is essential for stability during lifting operations; an unleveled crane can tip over, causing accidents.
- Making other personnel aware of hoisting activities: Informing other workers about crane operations ensures they can stay safe, avoid the swing radius, and coordinate their work accordingly.
Snap & solve any problem in the app
Get step-by-step solutions on Sovi AI
Photo-based solutions with guided steps
Explore more problems and detailed explanations
A. Barricading areas within the swing radius
B. Contacting power line owners
C. Leveling the crane
D. Making other personnel aware of hoisting activities