two pumps were required to pump the water out of a submerged area after a hurricane. pump a, the larger of the two pumps, can pump the water out in 24 hours, whereas it would take pump b 120 hours. both pumps were working for the first 6 hours until pump a broke down. how long did it take pump b to pump out the remaining water?
pump b pumped alone for hours.
Calculate the combined work rate and work completed in the first 6 hours
Determine the remaining work to be done
Calculate the time required for Pump B to complete the remaining work alone
Snap & solve any problem in the app
Get step-by-step solutions on Sovi AI
Photo-based solutions with guided steps
Explore more problems and detailed explanations
Two pumps were required to pump the water out of a submerged area after a hurricane. Pump A, the larger of the two pumps, can pump the water out in 24 hours, whereas it would take pump B 120 hours. Both pumps were working for the first 6 hours until pump A broke down. How long did it take pump B to pump out the remaining water?
Pump B pumped alone for <blank>84</blank> hours.