question 3 what aspects of a project can be impacted when approving cha…

Question

question 3
what aspects of a project can be impacted when approving change?
choose all options that best answer the question.
project business case
project resources
project swag
project end date
project budget

Explanation:

Brief Explanations

When approving a project change, the project business case (as it may need re - evaluation for alignment), project resources (e.g., manpower, materials may change), project end date (schedule can be affected), and project budget (costs may increase or decrease) are impacted. "Project swag" is not a standard project aspect related to change approval.

Answer:

A. Project business case
B. Project resources
D. Project end date
E. Project budget